Geelong Tunnel
Project dates: 2026 - 2027
The Geelong Tunnel first opened in 1876 and is a significant and historical piece of infrastructure on the V/Line network. We're delivering major maintenance works no the Geelong Tunnel in January 2027 so that it can continue to provide a vital connection for passengers for years to come.
Replacement bus services will operate between Geelong and Waurn Ponds Station during the Geelong Tunnel works. Passengers travelling from Geelong to Southern Cross Station will not be affected by the Geelong Tunnel works.
During these works the brick floor of the 150-year-old tunnel will be replaced with a new concete surface.
These works will improve the reliability of the tunnel and reduce the frequency of on-going maintenance.
The tunnel is 425m long, 150 years old and currently has temporary speed restrictions when trains are travelling through it.
Works will also include earthworks, track formation, drainage works and signalling and communications works.